CNST403: Planning and Scheduling (4 Credits)
|
Instructor: |
Dr. Bodapati ( Off Tel: 618-692-2825, Res Tel: 314-752-9306) Email Address:sbodapa@siue.edu Class Meets: Tuesdays & Thursdays; 2:00 - 3:50pm |
|
|
Text: | Construction Project Scheduling by Callahan, Quackenbush, and Rowings (Available at the SIUE Textbook Service for rental) |
|
|
Scheduling Software: | Primavera for Windows (Version 2.0). Student Versions of the Software with manual are available for $35 from Primavera. Check with Dr. Bodapati. |
|
|
Description: | Comprehensive survey of Critical Path Method (CPM) scheduling techniques including Arrow Diagram Method (ADM), Precedence Diagram Method (PDM), PERT and GANTT Charts. Project progress measurement and variance analysis. Approximately 50% of the course work involves application of Primavera to scheduling. |
|
|
Objective: | Prepare the construction student for planning and scheduling duties in all aspects of construction practice. Hands-on exposure to the scheduling software currently used by the industry. |
|
|
Instructions: | Completion of Assignments Email and Homepage |
|
|
Week 1 | Introduction: Course overview, scheduling basics and terminology. Class Assignment |
|
|
Week 2 | Schedule Development: Basics. Class Assignment |
|
|
Week 3 | CPM Schedules: Determining work activities, durations and logic; Arrow Diagram Method (ADM) Class Assignment |
|
|
Week 4 | CPM Calculations: Critical activities, early and late start times and float Class Assignment |
|
|
9/18/97 | Test #1 |
|
|
Week 5 | Precedence Diagram Method (PDM): Logic conventions, calculations Class Assignment |
|
|
Week 6 | Primavera ApplicationClass Assignment |
|
|
Week 7 | Primavera ApplicationClass Assignment |
|
|
Week 8 | Project Progress Measurement: Updating project progress Class Assignment |
|
|
10/16/97 | Mid-Term Examination |
|
|
|
|
Week 9 | Primavera Application: Project progress updating Class Assignment |
|
|
Week 10 | Primavera Application: Project progress updating Class Assignment |
|
|
Week 11 | Cost Loaded CPMS: Cost and schedule integration, cash flow analysis Class Assignment |
|
|
Week 12 | Primavera Application: Cost-loaded CPMs Class Assignment |
|
|
11/13/97 | Test # 3 |
|
|
Week 13 | Least cost Scheduling: Schedule Compression Class Assignment |
|
|
Week 14 | Thanksgiving Break: NO CLASSES |
|
|
Week 15 | Use of CPM in Delays and Claims Analysis Class Assignment |
|
|
Week 16 | course Review Class Assignment |
|
|
12/18/97 | Final Examination: 12:00 - 1:40pm |
|
|
Grading: |
15% Class assignments 10% Test #1 15% Mid-Term Examination 15% Test #3 10% Project Assignment 35% Final Examination |
|
|
References: | O’Brien, J.J., CPM in Construction Management, 4th edition, Mc-Graw Hill Inc., New York, 1993. Clough, R.H., and G.A. Sears, Construction Project management, 3rd edition, John Wiley & Sons, Inc., 1991. O’Brien, J.J., Construction Delay: Responsibilities, Risks and Litigation, Cahners Books International, Inc., 1976. Construction Planning & Scheduling, Associated General Contractors of America, January 1994, Publication No.: 1107.1. |
|