CNST403: Planning and Scheduling (4 Credits)

Southern Illinois University at Edwardsville
School of Engineering, Department of Construction


Instructor: Dr. Bodapati ( Off Tel: 618-692-2825, Res Tel: 314-752-9306)
Email Address:sbodapa@siue.edu
Class Meets: Tuesdays & Thursdays; 2:00 - 3:50pm


Text: Construction Project Scheduling by Callahan, Quackenbush, and Rowings
(Available at the SIUE Textbook Service for rental)


Scheduling Software: Primavera for Windows (Version 2.0). Student Versions of the Software with manual are available for $35 from Primavera. Check with Dr. Bodapati.


Description: Comprehensive survey of Critical Path Method (CPM) scheduling techniques including Arrow Diagram Method (ADM), Precedence Diagram Method (PDM), PERT and GANTT Charts. Project progress measurement and variance analysis. Approximately 50% of the course work involves application of Primavera to scheduling.


Objective: Prepare the construction student for planning and scheduling duties in all aspects of construction practice. Hands-on exposure to the scheduling software currently used by the industry.


Instructions: Completion of Assignments
Email and Homepage


Week 1 Introduction: Course overview, scheduling basics and terminology. Class Assignment


Week 2 Schedule Development: Basics. Class Assignment


Week 3 CPM Schedules: Determining work activities, durations and logic; Arrow Diagram Method (ADM) Class Assignment


Week 4 CPM Calculations: Critical activities, early and late start times and float Class Assignment


9/18/97 Test #1


Week 5 Precedence Diagram Method (PDM): Logic conventions, calculations Class Assignment


Week 6 Primavera ApplicationClass Assignment


Week 7 Primavera ApplicationClass Assignment


Week 8 Project Progress Measurement: Updating project progress Class Assignment


10/16/97 Mid-Term Examination




Week 9 Primavera Application: Project progress updating Class Assignment


Week 10 Primavera Application: Project progress updating Class Assignment


Week 11 Cost Loaded CPMS: Cost and schedule integration, cash flow analysis Class Assignment


Week 12 Primavera Application: Cost-loaded CPMs Class Assignment


11/13/97 Test # 3


Week 13 Least cost Scheduling: Schedule Compression Class Assignment


Week 14 Thanksgiving Break: NO CLASSES


Week 15 Use of CPM in Delays and Claims Analysis Class Assignment


Week 16 course Review Class Assignment


12/18/97 Final Examination: 12:00 - 1:40pm


Grading: 15% Class assignments
10% Test #1
15% Mid-Term Examination
15% Test #3
10% Project Assignment
35% Final Examination



References: O’Brien, J.J., CPM in Construction Management, 4th edition, Mc-Graw Hill Inc., New York, 1993.

Clough, R.H., and G.A. Sears, Construction Project management, 3rd edition, John Wiley & Sons, Inc., 1991.

O’Brien, J.J., Construction Delay: Responsibilities, Risks and Litigation, Cahners Books International, Inc., 1976.

Construction Planning & Scheduling, Associated General Contractors of America, January 1994, Publication No.: 1107.1.