Posted October 11, 2018
Facilities Management is in the process of hanging emergency egress floor plans at the north and south exits of Founders Hall. These large signs show the fastest route to evacuate the building in case of an emergency.
We continue to make progress on the excavation for the southwest tower and began pier drilling on October 10, 2018. Also, the atrium barriers between the first and second floors in Founders Hall are now complete, mitigating the amount of noise, dust, and debris entering occupied areas from the construction zone.